11.5 Plan Risk Responses

Decide, for each significant risk, what you will actually do about it.

Planning / Risk · ← PMBOK reference · See it on the map

Why it matters

A risk that is identified and scored but has no plan attached is still just a worry; this is the step that turns it into an action someone owns.

What done looks like

Every significant risk has an assigned response strategy and an owner.

First time tip

Name a single owner for each response, not a team. A response owned by everyone tends to be actioned by no one.

What you need (Inputs)

How you do it (Tools & Techniques)

What you get (Outputs)

Worked example

For the storm the committee books a marquee that covers the stage and names the site manager as its owner; for a cancellation it agrees a standby local act and names the bookings volunteer; for the late toilets it decides to accept the risk and says so in the register. Each response carries one name and a date by which it has to be in place.

Common pitfalls