Strategies for Threats

Risk technique · See it on the map

Runnable here

Choosing a deliberate response to a risk that would hurt the project if it happened.

When to use it

For every threat (a risk with a negative effect on the project) once it's scored highly enough to warrant a response beyond just watching it. This is the mirror image of strategies for opportunities, below — same decision structure, aimed at downside instead of upside.

When to avoid it

Don't force a formal strategy choice onto a risk so low in exposure that 'accept, revisit later' is obviously correct and would only be dressed up by a longer discussion. Also don't default every threat to 'mitigate' without considering avoid or transfer — mitigate is the comfortable middle choice and it's easy to reach for out of habit rather than fit.

Steps

What it produces

Common pitfalls

Worked example

A single-source component supplier is the sole vendor for a custom connector on a robotics build. The PM can't avoid the dependency (no second supplier exists) but negotiates a penalty clause for late delivery (transfer) and, separately, qualifies a slower backup part that could substitute if the primary slips more than three weeks (an active-acceptance fallback).

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.