12.1 Plan Procurement Management

Decide what the project will buy from outside, and how you will buy it.

Planning / Procurement · ← PMBOK reference · See it on the map

Why it matters

Deciding to buy something after the schedule already needs it leaves no time to shop around, and you end up paying more for less choice.

What done looks like

A procurement plan names what will be bought, from whom, and by when.

First time tip

Decide build-versus-buy for each item as early as possible. A late decision to buy forces a rushed purchase with far less negotiating room.

What you need (Inputs)

How you do it (Tools & Techniques)

What you get (Outputs)

Worked example

The renovation buys the shelving and the contractor's crew, while the library's own volunteers do the painting prep. Settling that in January is what leaves time to get three shelving quotes before the May delivery slot has to be booked.

Common pitfalls