6.4 Estimate Activity Durations

Estimate how long each activity will realistically take to finish.

Planning / Schedule · ← PMBOK reference · See it on the map

Why it matters

An optimistic guess here understates the whole schedule, and everything built on top of it — the finish date, the staffing plan — inherits that understatement.

What done looks like

Every activity carries a duration estimate with its basis and assumptions recorded.

First time tip

Give a range, not a single number, for anything you are not confident about. A range keeps the uncertainty visible instead of hiding it in one guess.

What you need (Inputs)

How you do it (Tools & Techniques)

What you get (Outputs)

Worked example

Repainting the reading room is three days for two painters, from the contractor's own rate. The wall repair is two to five days, because nobody has opened it yet — and that range is what keeps the doubt visible instead of buried in one number.

Common pitfalls

How driftless helps