Strategies for Overall Project Risk

Risk technique · See it on the map

Runnable here

Responding to a project's risk as one combined whole, not just risk by risk.

When to use it

At key decision points (major milestones, gate reviews, before committing to a firm deadline or price) when the question isn't 'what do we do about risk #14' but 'given everything we know is uncertain, how exposed is this project, and should we change course.'

When to avoid it

As a substitute for individual risk response — a project-level judgment that 'overall risk is moderate' doesn't tell anyone what to do about the specific vendor risk or the specific technical risk sitting in the register. Use both; neither replaces the other.

Steps

What it produces

Common pitfalls

Worked example

A construction PM reviews a register with eleven individually 'medium' risks and no single 'high' one, and could report the project as broadly healthy. Stepping back, four of those eleven risks share a dependency on the same crane subcontractor's schedule; if that subcontractor slips, four risks fire together. The PM reports overall project risk as elevated despite no individual entry crossing the 'high' threshold, and pulls forward a conversation about a backup crane arrangement.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.