7.3 Determine Budget

Add up the activity costs into an approved, time-phased budget.

Planning / Cost · ← PMBOK reference · See it on the map

Why it matters

The activity estimates alone do not say when money is needed, and a budget with no timing tells finance nothing useful about cash flow.

What done looks like

An approved cost baseline exists, showing planned spend against the schedule over time.

First time tip

Plot the budget as a curve against the schedule before you finalize it. A flat line rarely matches how spending actually happens over a project.

What you need (Inputs)

How you do it (Tools & Techniques)

What you get (Outputs)

Worked example

The activity estimates add up to $41,000, and spreading them across the schedule — demolition and paint in March, shelving in May when the supplier can deliver — is what tells the board it needs $18,000 available before April.

Common pitfalls