Season 4 Rollout
As of 2026-07-01 · Process map · Wizard · Schedule · Flow · Board · Weekly status · RAID log · Requirements & WBS · Team · Procurement calculator · Cost workbench · Quality workbench · Closeout · Schedule network · Decisions and meetings · Earned value calculator · Scope worksheet · Stakeholder assist · Decision tree · Probability and impact · Risk responses
Status
Process completeness 53%
- Integration
- Integration 43%
- Scope
- Scope 67%
- Schedule
- Schedule 67%
- Cost
- Cost 50%
- Quality
- Quality 67%
- Resource
- Resource 50%
- Communications
- Communications 33%
- Risk
- Risk 57%
- Procurement
- Procurement 33%
- Stakeholder
- Stakeholder 50%
EV 10,950 · CPI 1.095 · SPI 0.952 · EAC 13,699 · Budget 15,000
CV 950 (under budget) · SV -550 (behind plan)
Flow
Work in progress 0 items · throughput (last 7 days) 0 items · median cycle time no data yet · no release forecast yet. See the flow page.
Scorecard strategy
- Gross margin: amber (measured)
- Open escalations: red (measured)
- Release checklist completion: green (measured)
- Escaped defects: red (measured)
Live threats
RAID
Open risks 1 · open issues 1 · open change requests 1
Risk reserve suggested: 45,000.00 — the open register's residual exposure, from the risk-response planner.
Milestones
| Milestone | Target | Status |
|---|---|---|
| Sizzle reel delivery | 2026-06-07 | Missed slipped |
| Principal photography wrap | 2026-06-10 | Met |
| Premiere | 2026-06-21 | Pending |
| Picture lock | 2026-07-15 | Pending |
| Network delivery accepted | 2026-08-16 | Pending |