Weekly status — Season 4 Rollout

As of 2026-07-01 · Process map

Percent complete is 73%, stamped from the tasks — it is not entered here, so the reading can never disagree with the work done.

0 50 100 2026-07-01
The same trend as text: the date, percent complete and RAG of every snapshot, earliest first
DatePercentRAG
2026-07-0173%red
Planned value (PV) vs actual cost (AC); earned value shown as the current position — per-task progress history is not retained.
PV AC Budget

EV 10,950 · CPI 1.095 · SPI 0.952 · EAC 13,699 · Budget 15,000

The same S-curve as text: planned value and actual cost at each sampled point, in plot order, earliest first
PointPlanned (PV)Actual (AC)
11670
21,0000
31,8332,500
42,6672,500
53,5002,500
64,3335,500
75,3335,500
86,5008,300
97,7508,300
109,0008,300
1110,25010,000
1211,50010,000