Closeout — Season 4 Rollout
As of 2026-07-01 · Project hub
Milestones met1 of 3
Lessons learned0
Budget at completion15000.0
Variance at completion1301.37
Deliverable acceptance
1 of 3 milestones met.
| Milestone | Target date | Status |
|---|---|---|
| Principal photography wrap | 2026-06-10 | met |
| Premiere | 2026-06-21 | pending |
| Sizzle reel delivery | 2026-06-07 | missed |
Lessons learned
No lessons raised yet.
Final report summary
- Budget at completion
- 15000.0
- Estimate at completion
- 13698.63
- Variance at completion
- 1301.37
The full narrative sits in the project's assessment report; this is the same figures, never a second computation of them.
Where this comes from
PMBOK-6 process 4.7 (Close Project or Phase) · as of 2026-07-01.