Schedule — Season 4 Rollout

As of 2026-07-01 · Project hub · Weekly status

2026-07-01 Shoot schedule 100% Dailies review 100% Assembly edit 100% Rough cut 55% Music clearance 30% Colour grade 0% Sound mix 0% Broadcast QC 0% Delivery to network 0%
The same schedule as text: each task's planned window and progress, then each milestone's target date and status
ItemStartFinish or targetProgress
Shoot schedule2026-05-062026-06-10100% complete
Dailies review2026-05-132026-05-27100% complete
Assembly edit2026-05-272026-06-10100% complete
Rough cut2026-06-102026-07-1555% complete
Music clearance2026-06-172026-07-2230% complete
Colour grade2026-07-152026-07-290% complete
Sound mix2026-07-152026-07-260% complete
Broadcast QC2026-07-292026-08-100% complete
Delivery to network2026-08-102026-08-160% complete
Sizzle reel delivery (milestone)—2026-06-07Missed
Principal photography wrap (milestone)—2026-06-10Met
Premiere (milestone)—2026-06-21Pending
Picture lock (milestone)—2026-07-15Pending
Network delivery accepted (milestone)—2026-08-16Pending
Every dependency edge in this project's network: which task waits on which, its type, and any lag or lead in days
TaskDepends on
Assembly editDailies review (FS +0d)
Broadcast QCColour grade (FS +0d)
Broadcast QCMusic clearance (FS +0d)
Broadcast QCSound mix (FS +0d)
Colour gradeRough cut (FS +0d)
Dailies reviewShoot schedule (SS +7d)
Delivery to networkBroadcast QC (FS +0d)
Rough cutAssembly edit (FS +0d)
Rough cutShoot schedule (FS +0d)
Sound mixRough cut (FS +0d)