driftless
Search

Funding Limit Reconciliation

Cost technique · See it on the map

Runnable here

Reshaping planned spending so it never asks for more money than is actually available each period.

When to use it

Whenever the funding organization releases money on a schedule — annual appropriations, quarterly capital releases, tranche-based investor draws — that doesn't automatically match the project's natural spend curve. Check it as soon as a period-by-period funding schedule exists, not after a period's spend has already been planned past its limit.

When to avoid it

Don't reconcile against funding limits that are still provisional or under negotiation — smoothing the schedule against a number that later changes wastes the exercise. And don't treat this as purely a cost problem: reshaping planned spend to fit a funding limit almost always reshapes the schedule too, since the work that generates that spend has to move with it.

Steps

What it produces

Common pitfalls

Worked example

A public infrastructure project's total budget is fully approved at $6 million, but the funding authority releases it in three annual tranches of $2 million each. The baseline schedule, driven by construction sequencing, calls for $2.6 million of spend in year one. Reconciliation pushes $600,000 of year-one paving work (which had slack) into year two, bringing year one to $2.0 million exactly — but the paving activity's downstream dependent, landscaping, now can't start until three months later than originally planned, which the team flags and re-baselines the schedule to reflect.

Where it comes from: this technique is named by the PMBOK Guide, 6th edition. No clause number is recorded for it here — a guessed citation would be worse than none.