driftless
Search

To-Complete Performance Index

Cost technique · See it on the map

Runnable here

The cost efficiency remaining work must hit to land on a realistic target cost.

When to use it

Any time CPI is off 1.0 and someone's asking whether the project can still hit its original budget. Use TCPI against BAC — (BAC − EV) / (BAC − AC) — to answer 'can we still make the original number', and TCPI against a revised EAC — (BAC − EV) / (EAC − AC) — to check whether even that revised, more forgiving forecast is achievable at the efficiency the team has actually been running at.

When to avoid it

Don't present a TCPI-against-BAC figure as a plan without comparing it against the CPI the project has actually been achieving — a TCPI far above current CPI isn't a target, it's a number nobody has a believable way to hit, and presenting it as achievable is arithmetic fiction dressed up as a forecast.

Steps

What it produces

Common pitfalls

Worked example

On the same community-center renovation (BAC $850,000, EV $348,500, AC $410,000, CPI 0.85), TCPI against BAC is (850,000 − 348,500) / (850,000 − 410,000) = 501,500 / 440,000 ≈ 1.14 — the remaining work would need to run at 1.14 efficiency, well above the 0.85 the project has actually delivered so far, to still hit the original $850,000. Against the earlier EAC of $1,000,000 instead, TCPI = (850,000 − 348,500) / (1,000,000 − 410,000) = 501,500 / 590,000 ≈ 0.85 — exactly the efficiency already being achieved, meaning the revised forecast is the believable one and the original budget, at this point, is not.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.