driftless
Search

Earned Value Analysis

Cost technique · See it on the map

Runnable here

Comparing planned, completed, and spent work at one point in time to judge cost and schedule performance.

When to use it

Any time you have a baselined cost and schedule and need a defensible answer to 'are we in trouble' that isn't just a gut feeling. It earns its keep most on projects long enough, and with enough spend, that a manager can't just eyeball progress against the budget.

When to avoid it

Don't run it against a baseline nobody actually approved, or against progress percentages nobody actually measured — a fabricated percent complete produces a CPI that looks precise and means nothing. And a single EAC formula (see below) is the wrong call on a project whose cost performance is actively recovering or deteriorating, not holding steady.

Steps

What it produces

Common pitfalls

Worked example

A community-center renovation has a BAC of $850,000. At the six-month as-of date, the baseline says $410,000 should have accrued (PV). Progress reports put earned value (EV) at $348,500, against $410,000 actually spent (AC) so far. CPI = 348,500 / 410,000 = 0.85 — the project is getting 85 cents of planned work for every dollar spent. SPI = 348,500 / 410,000 = 0.85 too, coincidentally the same figure here, meaning progress is also running behind the baseline's pace. The resulting EAC (BAC / CPI = 850,000 / 0.85 ≈ $1,000,000) says the job will cost roughly $150,000 more than planned if the last six months' cost performance holds — the project manager reports that as a conditional forecast, not a promise, and starts investigating which trade's overruns are driving the 0.85.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.