Prompt Lists
Risk technique · See it on the map
Guide only — The checklist a reader fills in IS the technique; no figure follows it.
Working through a predetermined list of risk categories to surface risks a free-form discussion would miss.
When to use it
During Identify Risks, after the team's own brainstorming and interviews have run dry — a prompt list (a category framework like PESTLE, or a project-specific risk breakdown structure) forces a pass through categories nobody happened to think of on their own.
When to avoid it
As the only identification technique, or as a checkbox exercise run without engaging with what each category actually implies for this project. A prompt list surfaces categories to think about; it doesn't do the thinking.
Steps
What it produces
- Risk register entries surfaced by a category the team had not yet considered.
Common pitfalls
- Running the list as a box-ticking exercise, recording nothing specific to the project under most categories.
- Treating it as a complete identification technique instead of a supplement to brainstorming and interviews.
Worked example
Having exhausted the team's own ideas, the PM runs the retrofit through a construction-specific prompt list. The 'permitting' category surfaces a risk nobody had raised: the historic district's design review board could require a resubmission if the exterior finish changes.
Source
- PMBOK-6 §11.2.2.5
Where it comes from: this technique is named by the PMBOK Guide, 6th edition.