Risk technique · See it on the map

Guide only — The checklist a reader fills in IS the technique; no figure follows it.

Working through a predetermined list of risk categories to surface risks a free-form discussion would miss.

When to use it

During Identify Risks, after the team's own brainstorming and interviews have run dry — a prompt list (a category framework like PESTLE, or a project-specific risk breakdown structure) forces a pass through categories nobody happened to think of on their own.

When to avoid it

As the only identification technique, or as a checkbox exercise run without engaging with what each category actually implies for this project. A prompt list surfaces categories to think about; it doesn't do the thinking.

Steps

What it produces

Common pitfalls

Worked example

Having exhausted the team's own ideas, the PM runs the retrofit through a construction-specific prompt list. The 'permitting' category surfaces a risk nobody had raised: the historic district's design review board could require a resubmission if the exterior finish changes.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.