Stakeholder Engagement Assessment Matrix

Stakeholder technique · See it on the map

Runnable here

A table comparing a stakeholder's current involvement against the involvement a project actually needs from them.

When to use it

When a stakeholder register alone doesn't tell you what to do next: use this once you know who the stakeholders are and need a plan for closing the distance between where each one stands today and where the project needs them to stand.

When to avoid it

Don't run it before a basic stakeholder analysis exists — there's nothing to assess a gap against. And don't run it in driftless expecting to record the result: this product stores only interest and influence (each low, medium, or high) on the stakeholder record, with no current-versus-desired engagement field at all. A reader can work through the technique on paper, but there is nowhere here yet to capture what it produces.

Steps

What it produces

Common pitfalls

Worked example

On a hospital scheduling rollout, the head nurse starts out resistant — she wasn't consulted on the pilot design — while the project needs her leading, since staff will follow her lead over any memo from IT. The gap between resistant and leading is the largest on the matrix, so the team schedules a working session with her before anyone else, rather than sending the standard rollout email to the whole department.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.