Pre Assignment

Resource technique · See it on the map

Runnable here

Naming who will do the work before the project is even approved or planned.

When to use it

Use it when the assignment is already a fact you can't undo: a proposal or contract named a specific person or firm, a specialist skill exists in exactly one person in the business, or a sponsor made the assignment a condition of funding the project at all.

When to avoid it

Don't reach for pre-assignment as a convenience just because a name comes to mind first. Locking an assignment before the plan exists removes a degree of freedom you may need later: if the schedule shifts and that person is unavailable in the window that now matters, there is no fallback because no one else was ever considered. Run the estimate first and pre-assign only what genuinely cannot be otherwise.

Steps

What it produces

Common pitfalls

Worked example

A regional bakery chain wins a contract to supply a grocery partner, and the contract names the chain's head baker, Priya, as the person who must sign off on the new product line's recipe scaling. The PM sets Priya as assignee on the recipe-scaling task the day the project is chartered, before any other activity resource estimating happens, and flags in the plan that the assignment is contractual, not a scheduling convenience.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.