Influencing
Resource technique · See it on the map
Guide only — Influencing without authority is practiced, not run.
Getting cooperation from people the project manager has no formal authority over, using relationships, evidence, and persuasion instead of a reporting line that doesn't exist.
When to use it
Use it constantly in a matrixed or cross-department project, where most of the people whose cooperation the plan depends on don't report to the PM: getting a department to prioritize a task, getting a stakeholder to make a timely decision, getting a peer PM to release a shared resource early.
When to avoid it
Don't reach for influence when you actually have authority — asking permission for something you're entitled to decide trains people to expect you to ask next time too. And don't lean on influence alone when a decision genuinely needs escalating: spending weeks persuading a peer to do what a sponsor could simply direct is a slower path to the same place.
Steps
What it produces
- Cooperation obtained without an escalation, and the relationship still intact afterward
Common pitfalls
- Mistaking charm for influence — a favor granted once because someone likes you doesn't survive repeated asks with nothing offered back.
- Over-using influence on people who actually need a decision escalated, which leaves a real authority gap unaddressed while looking like progress.
- Burning a relationship on a low-stakes ask, leaving nothing in reserve for the time the project genuinely needs it.
Worked example
A hospital-equipment installer's PM needs a facilities technician who reports to building operations, not to her, to reschedule a maintenance window around the install. Rather than escalating to the facilities director immediately, she shows the technician the specific two-hour overlap causing the conflict and offers to shift the install crew's start time to give him a wider window, and he agrees without anyone above either of them getting involved.
Source
- PMBOK-6 §9.5.2.1
Where it comes from: this technique is named by the PMBOK Guide, 6th edition.