Communication Requirements Analysis

General technique · See it on the map

Guide only — Deciding who needs what information is a judgment call informed by the stakeholders assistant, not a computed procedure of its own.

Working out who needs which information, in what form, and how often, before choosing a channel for any of it.

When to use it

At the start of planning communications, before picking any method or technology: for each stakeholder, determine what they need to know, why, and how often, from the stakeholder register and the project's organizational structure and reporting lines.

When to avoid it

Don't skip straight to a channel or a cadence 'because that's what the last project used' — a communications plan built without naming the actual information need behind each line tends to over-communicate to people who don't need it and under-communicate to the few who do.

Steps

What it produces

Common pitfalls

Worked example

For the retrofit, the site foreman needs daily sequencing detail, while the client sponsor needs only a weekly summary with a decision flagged when one is pending.

Source

Where it comes from: this technique is named by the PMBOK Guide, 6th edition.