Schedule Network Analysis
Schedule technique · See it on the map
Runnable here
The general term for techniques that build a project schedule from its task dependencies.
When to use it
Reach for this framing when you need to talk about analyzing the schedule network as a category — choosing which specific technique(s) below fit the situation — rather than as a standalone technique with its own distinct steps.
When to avoid it
Don't cite "schedule network analysis" in place of naming the actual technique you used — it's a category label, and reporting it as the method obscures whether the real work was critical path method, resource optimization, or something else, each of which has different assumptions and different failure modes.
Steps
What it produces
- Whatever the chosen specific technique produces — a critical path, a resource-leveled schedule, a buffer-tracked chain, or a what-if comparison — read through this umbrella framing as "the current best schedule derived from the network".
Common pitfalls
- The umbrella term gets used as if it were itself a technique with a procedure, producing vague advice ("do schedule network analysis") that doesn't tell anyone what to actually do next.
- A what-if scenario run is performed once to answer a specific question and then treated as the ongoing schedule, rather than as a single scenario compared against the baseline.
- Analysis stops after the first pass even though the network keeps changing, so the schedule's "current" critical path or resource picture is quietly stale.
Worked example
Ahead of a board presentation, a program manager runs three separate schedule network analyses on the same dependency network: a straight critical path run for the base case, a resource-optimization run reflecting a hiring freeze, and a what-if run modeling a two-week permit delay — presenting all three as distinct scenarios rather than a single number.
Source
- PMBOK-6 §6.5.2.1
Where it comes from: this technique is named by the PMBOK Guide, 6th edition.