Audits
Quality technique · See it on the map
Runnable here
A structured, independent check of whether the project's actual quality process was followed — as distinct from whether the product it produced meets its requirements.
When to use it
On a routine cadence, before a major deliverable handoff, after a serious quality escape to check whether the process failed or was simply skipped, or where a certification or compliance obligation requires it.
When to avoid it
When the process being audited is one the team doesn't believe is workable — fix the process first, or the audit measures compliance with a rule nobody follows and becomes theatre. Also avoid auditing when the real question is whether one specific product is good; that's testing/inspection, not an audit.
Steps
What it produces
- An audit report listing findings against the stated process.
- Agreed corrective actions with owners and a follow-up date.
- Good practices identified that are worth reusing elsewhere on the project.
Common pitfalls
- Auditing compliance with a process nobody believes in — teams learn to perform for the audit rather than change how they work; fix or retire the process instead.
- An auditor who is also accountable for the result being audited, so findings get softened.
- Treating a clean audit as proof the product is good. An audit checks whether the process was followed, not whether the output meets spec — pair it with testing or inspection for that question.
- Findings that nobody is assigned to actually fix.
Worked example
At Larch & Rowe, a quarterly audit of the change-order approval process finds that 6 of 20 sampled change orders were verbally approved on site, with paperwork filed after the fact. The audit doesn't fault the PM's workmanship — it flags that the approval process, which requires a signature before work starts, doesn't fit how change orders actually arise on a job site. The corrective action revises the process to allow a documented verbal approval with a 24-hour paper follow-up, rather than keep failing everyone against a rule nobody follows.
Source
- PMBOK-6 §8.2
Where it comes from: this technique is named by the PMBOK Guide, 6th edition.