Weekly status — Fleet Modernization

As of 2026-07-01 · Process map

Percent complete is 78%, stamped from the tasks — it is not entered here, so the reading can never disagree with the work done.

0 50 100 2026-07-01
The same trend as text: the date, percent complete and RAG of every snapshot, earliest first
DatePercentRAG
2026-07-0178%green
Planned value (PV) vs actual cost (AC); earned value shown as the current position — per-task progress history is not retained.
PV AC Budget

EV 31,200 · CPI 1.114 · SPI 1.017 · EAC 35,897 · Budget 40,000

The same S-curve as text: planned value and actual cost at each sampled point, in plot order, earliest first
PointPlanned (PV)Actual (AC)
16670
23,3330
36,6679,000
49,3339,000
512,6679,000
615,33317,500
718,66717,500
821,33317,500
924,88923,500
1026,66723,500
1128,88928,000
1230,66728,000