driftless Fleet Modernization
Search As of 2026-07-01

A greyed-out label above marks a link this fixed demo does not ship: only the story project's pages go this deep, and an action a live reader could take here (signing in, applying a technique) is disabled in a read-only export.

Fleet Modernization

As of 2026-07-01 · Process map · Wizard · Schedule · Flow · Board · Weekly status · RAID log · Requirements & WBS · Team · Procurement calculator · Cost workbench · Quality workbench · Closeout · Schedule network · Decisions and meetings · Earned value calculator · Scope worksheet · Stakeholder assist · Decision tree · Probability and impact · Risk responses

Status

Process completeness 49%

Integration
Integration 57%
Scope
Scope 50%
Schedule
Schedule 67%
Cost
Cost 50%
Quality
Quality 33%
Resource
Resource 33%
Communications
Communications 33%
Risk
Risk 57%
Procurement
Procurement 33%
Stakeholder
Stakeholder 50%

EV 31,200 · CPI 1.114 · SPI 1.017 · EAC 35,897 · Budget 40,000

CV 3,200 (under budget) · SV 533 (ahead of plan)

Flow

Work in progress 2 items · throughput (last 7 days) 1 item · median cycle time 7.0 days · likely release 2026-07-29. See the flow page.

Scorecard strategy

amber Reduce fleet waste · Internal Operations · direct contribution

Live threats

No live threats.

RAID

Open risks 0 · open issues 1 · open change requests 0

Risk reserve suggested: 0.00 — the open register's residual exposure, from the risk-response planner.

Milestones

Milestones for Fleet Modernization, with target date and status
MilestoneTargetStatus
Fleet go-live2026-06-17 Met