Weekly status — Archive Digitization

As of 2026-07-01 · Process map

Percent complete is 78%, stamped from the tasks — it is not entered here, so the reading can never disagree with the work done.

0 50 100 2026-07-01
The same trend as text: the date, percent complete and RAG of every snapshot, earliest first
DatePercentRAG
2026-07-0178%amber
Planned value (PV) vs actual cost (AC); earned value shown as the current position — per-task progress history is not retained.
PV AC Budget

EV 12,400 · CPI 0.954 · SPI 1.025 · EAC 16,774 · Budget 16,000

The same S-curve as text: planned value and actual cost at each sampled point, in plot order, earliest first
PointPlanned (PV)Actual (AC)
13450
21,7240
33,1035,500
44,1385,500
55,5175,500
66,8975,500
78,2768,700
89,6558,700
910,5588,700
1010,9778,700
1111,53513,000
1212,09313,000